The contractor has finished the concrete walks and driveway pavement on the south side of Wisconsin Avenue and anticipates switching traffic to the newly constructed roadway by the end of this week. Crews will begin pavement removal on the north side of Wisconsin Avenue starting the week of August 6.
Stage 2: The north side of Wisconsin Avenue from North 20th to North 38th streets will be closed for construction. Motorists will travel on the south side of the street.
- North 24th Street will remain open to traffic.
- North 27th Street will remain open to traffic.
- North 35th Street will remain open to traffic with one through lane of traffic in each direction. Large trucks will not be allowed to make turns onto, or from, Wisconsin Avenue.
As a reminder, the weekly construction meetings to address any concerns your business may have about the project and share construction schedule details are held every Thursday at 10:30 a.m. located at the field office, 455 North 39th Street, Unit 6.